|
Fish Movement at the Springbank Dam - Thames River, Ontario
PHASE 2 -
POST-CONSTRUCTION MONITORING - 2008
The City of
London, Ontario commissioned this study with the objective
of comparing post-construction data related to the
movement of various fish species during the spring before
Springbank dam closure. Specific objectives were to
determine:
1) If the Springbank dam is a barrier to fish
movement,
2) Fish attraction to the dam structure,
3) The
degree of upstream and downstream fish passage,
4) Timing
of fish passage,
5) Fish passage efficiency,
6) Thermal
and hydraulic conditions at the dam site during fish
passage
7) The duration of migration (i.e. migration
windows) for the different species of fish monitored from
the Thames River.
The purpose of this report is to
summarize fish movement after construction of the new dam
gates and to compare post-construction fish-movement data
with
pre-construction baseline data collected in 2006.
POST-CONSTRUCTION MONITORING OF FISH PASSAGE AT THE
SPRINGBANK DAM
EXECUTIVE SUMMARY

Springbank dam
in 2006 pre-construction with stoplog gates (above) and
post-construction of hydraulic gates in 2008 (above).
The City of London and the Upper
Thames River Conservation Authority originally contracted
Biotactic Incorporated in 2006 to design and conduct a
study to collect baseline data related to fish movement at
the Springbank dam in the spring before stoplogs were
installed and the dam operated. The baseline data were
compared with similar information collected
post-construction in 2008 to address Provincial and
Federal directives pertaining to the maintenance or
enhancement of the status quo related to fish
movement at the Springbank dam. Radio-telemetry was used
to track the movement of 120 radiotagged white suckers,
shorthead redhorse and smallmouth bass (twenty fish of
each species, each monitoring year) at the Springbank dam
from April 14, 2006 to June 27, 2006 and again from April
19, 2008 to June 15, 2008. All fish were collected from
areas upstream from the dam and released downstream after
radio-tag implantation. In 2008, fish approached the dam
as readily as they did in 2006, but only half as many fish
of each species were eventually able pass over the dam
gates. Of the two catostomid species (early migrating
white suckers and mid season migrating shorthead redhorse)
that were monitored; both readily approached the dam, but
white sucker took significantly longer to pass through the
dam and shorthead redhorse passed through the dam
significantly faster in 2008. Late spring upstream
migrating smallmouth bass took longer to pass through the
dam in 2008 and some used the structure as habitat.
Pre-construction data from 2006, compared with
post-construction data from 2008 indicates that the Springbank dam is not a barrier to fish movement prior to
dam closure, and can be summarized as follows:
-
Pre-construction attraction
efficiencies of white sucker, shorthead redhorse and
smallmouth bass in 2006 were statistically similar to
post-construction attraction efficiencies in 2008. These
values (reported as efficiency with 95 % confidence
interval in parentheses) are:
|
Fish Species |
2006 |
2008 |
|
White sucker |
90 %
(70 % - 97
%) |
80 %
(58 % - 92
%) |
|
Shorthead redhorse |
80 %
(58 % - 92
%) |
100 %
(84 % - 100
%) |
|
Smallmouth bass
|
95 %
(76 % - 99
%) |
95 %
(75 % - 99
%) |
-
Pre-construction passage efficiencies of white
sucker, shorthead redhorse and smallmouth bass in 2006
were statistically higher than post-construction passage
efficiencies in 2008. These values (reported as efficiency
with 95 % confidence interval in parentheses) are:
|
Fish Species |
2006 |
2008 |
|
White sucker |
94 %
(74 % – 97
%) |
50 %
(28 % – 71
%) |
|
Shorthead redhorse |
80 %
(58 % – 92
%) |
55 %
(34 % – 74
%) |
|
Smallmouth bass |
95 %
(76 % – 99
%) |
53 %
(32 % – 73
%)
|
-
Most fish rapidly approached
and swam upstream through the dam structure in 2006. Fish
readily approached the dam in 2008, but white sucker and
smallmouth bass were more delayed while passing through
the dam. The mean time (± standard error) required for
each species to pass the Springbank dam was:
|
Fish Species |
2006 |
2008 |
|
White sucker |
5.2
(± 7.4 min) |
24.23
(± 22.65
min) |
|
Shorthead redhorse |
3.5
(± 2.6 min) |
2.22
(± 1.66
min) |
|
Small mouth bass |
16.7
(± 22.1
min) |
27.94
(± 27.43
min) |
-
Environmental factors such as mean river discharge,
air temperatures and water temperatures at Springbank dam
as well as lengths of individual fish were recorded in
2006 and 2008. Statistical comparisons were made from the
entire study period and one week after release of each
species to determine the possible influence of factors
external to dam construction. It was concluded that air
and water temperature changes and water level changes were
significantly different; however air and water
temperatures had a negligible effect on fish behaviour.
River level changes reflected different river flow
conditions in 2008 compared to 2006. Other water level
factors such as hydraulic conditions over the new dam
gates did vary over the course of the study due to gate
testing and the north gate failed to open fully and did
not lie completely flat on the river bottom as designed.
-
Further monitoring is required in 2009 and perhaps
2010/2011, with larger sample sizes of radio-tagged
individuals if possible. These additional data are
required to refine statistical comparisons related to
baseline conditions. During monitoring,
as many factors as possible must be
kept constant related to Springbank dam, as well as
capturing, handling and release of fish. For example,
releases of radio-tagged fish should be conducted under
similar thermal and hydraulic conditions, at similar dates
and times each year. Dam gates should be lowered as much
as possible and remain lowered throughout the study period
(except for testing purposes outside of peak periods of
upstream fish migration). Upstream fish migration occurred
slightly later in 2008 compared to 2006 due to variation
in natural environmental conditions. Some variables, such
as river flow, water temperature, and mechanical
malfunction are somewhat unpredictable, and control of
these dynamic factors will remain a key challenge for this
monitoring project.
-
A comparison of the data sets from
2006 and 2008 shows statistically, or mathematically
significant differences regarding attraction and passage
efficiencies. Observations made either directly or videographically suggest that the biological significance
of measured attraction and passage efficiencies
may differ from mathematical
significance. In other words, there was evidence in both
2006 and 2008 that multiple species other than the
selected 3 targeted species, move with relative ease over
the Springbank dam gates.
2009 Post-Construction Fish
Monitoring Report - HERE
|